NZTA Road Space Bookings: your questions answered
NZTA ran two webinars on Road Space Bookings before they became mandatory on 9 November 2026, and people asked a lot of questions. Most came back to the same few things: two RCAs on one job, the deployment sheet, deadlines, short-notice work and detours. Here are the answers we could find, each with its source. Where NZTA hasn't answered yet, we say so and tell you what we do know.
Each answer is marked NZTA answered when NZTA answered it at a webinar, In NZTA's guidelines when NZTA's Guidelines for road space bookings (October 2026) cover it, and Not answered yet when nobody has said yet. We've left out the names of the people who asked. New to bookings? Start with What is an NZTA Road Space Booking? The plain-English version.
On this page
Two RCAs on one job
The question asked most at both webinars.
The council is the primary RCA, but some of my signs are on the state highway. Do I make a booking? NZTA answered
No. When another RCA is the primary on a TMP that covers two networks, bookings aren't used for that TMP, and at this stage bookings only work for worksites on the state highway network. You still send NZTA an Early Access Request for the signs on the state highway, and you only enter the state highway impact, not the impact on the local road.
Source: NZTA's webinar 1 Q and A overview; NZTA's answer in the 4 November webinar chat.
Do I still fill in the deployment sheet for the state highway part? NZTA answered
Yes. Asked exactly this at the 4 November webinar, NZTA said the deployment sheet is still needed until it confirms it is being retired, network by network.
Source: NZTA's answer in the 4 November webinar chat.
Should I make NZTA the primary RCA so I can use bookings? Not answered yet
Asked at the 4 November webinar, and not answered in the chat. What NZTA did say: the primary RCA decides whether bookings are used, and NZTA is looking at the "edge cases" where signs need to go on the state highway. Until it says more, ask the RTTMC through myWorksites on your TMP.
Source: NZTA's answer in the 4 November webinar chat.
A one-way system on a local road and a lane closure on the highway: one TMP or two? NZTA answered
NZTA's answer: a TMP is needed for the lane closure on the state highway, and that TMP is where the booking for the state highway goes. NZTA said it will confirm how the two networks work together as more councils join.
Source: NZTA's answers in the 4 November webinar chat.
Which councils use bookings? NZTA answered
At 4 November NZTA was the only RCA using bookings. Auckland is opting in from 30 November 2026, and Invercargill and Southland are piloting them. Every other council still runs its own process: see its page in our RCA Library.
Source: NZTA's answer in the 4 November webinar chat; myWorksites Help Center.
The deployment sheet
Do I still fill in the deployment sheet? NZTA answered
Yes, alongside your bookings, for now. NZTA will drop it one network at a time, once enough worksites on that network use bookings and the site status updates (NZTA measures the share of worksites that do). There's no date yet. NZTA's reason: until nearly everyone books, the bookings alone can't show everything on the road.
Source: NZTA's answers in the 4 November webinar chat; webinar 1 Q and A overview and slide pack.
The booking deadline is 4pm Wednesday but the deployment sheet says 5pm. Which is it? In NZTA's guidelines
Both, for different things. Bookings must be in before 4pm on the Wednesday before the work week. The RTTMC deployment spreadsheet's own instructions say to email it to [email protected] by 5pm each Wednesday for the following week. A work week runs Sunday to Saturday for both. Send both by 4pm and you can't get it wrong.
Source: NZTA guidelines, section 2; instructions inside the RTTMC deployment spreadsheet.
Booking rules and timing
When do I make the booking? In NZTA's guidelines
For a site-specific TMP, at the same time as you submit the TMP. For a PARS (a reusable TMP for repeated work), once the PARS has been accepted, one booking for each works package. Short non-invasive jobs, such as surveys and inspections, don't need a booking.
Source: NZTA guidelines, section 1.
When will I know my booking is OK? NZTA answered
The RTTMC goes through bookings at its Thursday Network Access Coordination meeting, so a booking in by 4pm Wednesday is looked at the next day.
Source: NZTA's answer in the 4 November webinar chat; webinar 1 slide pack.
Does that mean site-specific TMPs go in earlier? NZTA answered
Yes. With bookings needed by the Wednesday before the work week, a site-specific TMP has to go in more than two weeks ahead to be through in time. NZTA says that's intended: it wants work planned and coordinated earlier.
Source: NZTA's webinar 1 Q and A overview.
If my TMP is sent back for changes, do I lose my booking? Not answered yet
Asked at the 4 November webinar, not answered. What we know: for a site-specific TMP the booking is part of the TMP approval process, so it is looked at along with the TMP. Ask the RTTMC through myWorksites on your TMP.
Source: NZTA's webinar 1 Q and A overview.
Can I change the booking dates after the TMP is accepted? NZTA answered
Yes, booking dates can change. If only the TMP's dates change, NZTA prefers the TMP Extension Request Form: don't change the dates inside the TMP itself, upload the form to a layout, and update the dates in myWorksites under both Worksite and TMP, before the TMP expires. Changing dates inside the TMP means NZTA has to review the whole TMP again.
Source: NZTA's answer in the 4 November webinar chat; webinar 1 Q and A overview.
Can I use "lane closure" on a road with one lane each way? In NZTA's guidelines
No. In NZTA's standard terms, a lane closure is only for roads with more than one lane in each direction, such as Auckland's motorways. Closing a lane on a two-lane road with traffic taking turns is "Stop/go MTC (alternating flow)". Both are Medium impacts.
Source: NZTA guidelines, standard TTM descriptors table.
Do I need a separate unattended impact every time? In NZTA's guidelines
Only when what drivers see changes. Stop/go by day with signs and a temporary speed limit left out overnight: two impacts, and the unattended one covers every hour the crew isn't there, weekends included. A shoulder closure that stays the same day and night: one impact. Everything packed up at the end of each day: no unattended impact at all.
Source: NZTA guidelines, section 5 and scenarios 1 to 3.
Someone else is booked where I need to work. What happens? NZTA answered
You can talk to the other applicant, or the RTTMC looks at it with the network team and decides what goes ahead and in what order. Booking early helps when two jobs clash. Asked how you know an early booking is real when NZTA encourages booking before the details are certain, NZTA didn't answer in the chat.
Source: NZTA's answer in the 4 November webinar chat; NZTA guidelines, section 2.
Do my existing TMPs turn into bookings? NZTA answered
Not by themselves. For site-specific TMPs you add bookings by hand for future work. myWorksites can convert a PARS for you: ask through the support button inside myWorksites.
Source: NZTA's webinar 1 Q and A overview; NZTA's answer in the 4 November webinar chat.
Is a booking reference kept while my TMP is a draft? NZTA answered
Yes. Once a reference is created, no other TMP or booking can use it.
Source: NZTA's answer in the 4 November webinar chat.
What about projects that run for years? NZTA answered
A booking can run longer than 12 months, but some parts, such as regulatory devices, can only be agreed for 12 months at a time and need agreeing again. NZTA wants long bookings avoided where possible, and asks you to contact the RTTMC about multi-stage long-term projects.
Source: NZTA's webinar 1 Q and A overview; NZTA guidelines, section 7.
PARS and Early Access Requests
For PARS work, do I need an Early Access Request, a deployment sheet and a booking? NZTA answered
For significant activities under a PARS, yes to the Early Access Request: it tells the RTTMC the work needs a look and maybe a 3Cs discussion. You make a booking for each works package, and the deployment sheet still applies for now. NZTA said there's confusion about Early Access Requests for PARS work and that it will issue more guidance.
Source: NZTA's webinar 1 Q and A overview; NZTA's answer in the 22 October webinar chat.
Does mobile or semi-static PARS work need a booking? In NZTA's guidelines
Short non-invasive work, such as inspections, doesn't. Mobile operations and semi-static operations are both standard Medium impacts, so work that needs them is booked like any other.
Source: NZTA guidelines, section 1 and the standard TTM descriptors table; NZTA's answer in the 4 November webinar chat.
Short notice, emergencies and small jobs
Weather closures and emergency repairs: booking first, after, or not at all? Not answered yet
Asked at the 4 November webinar, not answered. Ask the RTTMC ([email protected]) how it wants urgent work recorded.
Small customer-driven jobs that are only confirmed days before? Not answered yet
Asked by utility contractors at the 4 November webinar, not answered. What we know: the 4pm Wednesday deadline still applies, and booking dates can change later, so booking the likely week early and moving it is better than missing the cut-off.
Source: NZTA guidelines, section 2; NZTA's answer in the 4 November webinar chat.
Does every STMS need a myWorksites login by 9 November? NZTA answered
NZTA wants it as soon as possible but said it will allow some leniency while everyone gets set up. The STMS needs the STMS role, and their company must be added to the TMP.
Source: NZTA's answer in the 4 November webinar chat; myWorksites Help Center.
Detours
How do I book a detour? In NZTA's guidelines
As impacts inside the same booking, one for each direction of the detour, each clearly labelled with the direction of traffic. In NZTA's Desert Road example, each direction takes two parts because of how myWorksites draws detour routes.
Source: NZTA guidelines, section 6 and scenario 5.
My detour uses another RCA's roads. Do I need a second TMP just to book it? Not answered yet
Raised at the 4 November webinar as extra time and duplication. NZTA asked for the details at [email protected] and hasn't answered publicly yet.
Source: NZTA's answer in the 4 November webinar chat.
Still waiting on NZTA
Open at 6 November 2026. We'll update this page when NZTA answers.
- Making NZTA the primary RCA on a two-network TMP.
- Whether a TMP sent back for changes keeps its bookings.
- Emergency, weather and urgent work.
- Short-notice customer-driven jobs.
- Detours on another RCA's roads.
- Whether you're told when someone else edits your booking.
- Whether the booking form fills itself from a TMP uploaded later.
For what each role does, see NZTA Road Space Bookings on state highways: what designers, contractors and STMS need to know.
Questions
Do I make a Road Space Booking if the council is the primary RCA?
No. When another RCA is the primary on a TMP that covers two networks, bookings aren't used for that TMP. You still send NZTA an Early Access Request for signs on the state highway, entering only the state highway impact, and the deployment sheet still applies.
Do I still need the RTTMC deployment sheet with Road Space Bookings?
Yes, for now. NZTA will retire it network by network once enough worksites use bookings. There is no date yet.
What is the deadline for NZTA Road Space Bookings?
Before 4pm on the Wednesday before the work week, which runs Sunday to Saturday. The RTTMC looks at bookings at its Thursday coordination meeting. The deployment spreadsheet's own deadline is 5pm Wednesday, so send both by 4pm.
Can I change Road Space Booking dates after the TMP is accepted?
Yes, booking dates can change. For a date-only change to the TMP itself, use NZTA's TMP Extension Request Form instead of editing the dates in the TMP.
Can I use lane closure as the impact on a two-lane road?
No. NZTA's lane closure term is only for roads with more than one lane in each direction. Traffic taking turns through one lane is Stop/go MTC (alternating flow). Both are medium impacts.
Sources
- NZTA, Guidelines for road space bookings, October 2026: https://nzta.govt.nz/assets/Roads-and-Rail/accessing-our-state-highways/nzta-guidelines-for-road-space-bookings-october-2026.pdf (checked 6 November 2026)
- NZTA, The end-to-end NZTA TTM process within myWorksites, webinar Q and A overview (22 October 2026): https://www.nzta.govt.nz/assets/Roads-and-Rail/accessing-our-state-highways/webinar-1-QA-overview.pdf (checked 6 November 2026)
- NZTA, Full NZTA TTM process in myWorksites, webinar 1 slide pack, 22 October 2026: https://www.nzta.govt.nz/assets/Roads-and-Rail/accessing-our-state-highways/RSB-webinar-1-slide-pack.pdf (checked 6 November 2026)
- NZTA, Showcasing the new Road Space Booking functionality, webinar, 4 November 2026 (answers quoted here are from the webinar's Q and A chat, which is not in the recording): https://www.youtube.com/watch?v=vTSGBUjx46g (checked 6 November 2026)
- NZTA, RTTMC deployment spreadsheet (instructions on its first sheet), from Managing access to the state highway: https://nzta.govt.nz/roads-and-rail/accessing-our-state-highways/managing-access-to-the-state-highway (checked 6 November 2026)
- myWorksites Help Center, TMPs with Road Space Bookings: https://help.myworksites.co.nz/en/articles/16450884-tmps-with-road-space-bookings (checked 6 November 2026)
Last checked: 6 November 2026