Library

Waimate District Council

What Waimate District Council asks for when you lodge a Corridor Access Request, with the page each answer came from.

Region
Canterbury
Type
District council
Authority website
www.waimatedc.govt.nz

This is our summary of what the authority publishes. Check the authority's own page before you lodge.

Lodging soon? Check your TMP with the Xuro Review Engine before it goes in. See the Review Engine

Submitting

Where to submit a CAR

No online portal is named on the pages checked. The council publishes a Corridor Access Request form (PDF) and TMP forms to complete, and sends questions to the roading team by email or phone.

Sources (1)
When a CAR is needed

Utility operators must complete a CAR for any work in the public road area, including excavating, drilling, resurfacing and installing pipes, cables and poles (the list is not exhaustive). The 2026/27 fee schedule also prices private corridor access requests, and requires a preliminary notification for all project works.

Sources (2)
TMP submission

A TMP is also required, using either a full form or a shortened form depending on complexity. Use the full form when the work has several phases or delays, such as resealing, shoulder widening or road reconstruction. The forms are PDFs on the council site. Where to send them was not stated on the page.

Sources (1)
Standard accepted

Not found yet

Local conditions

Not found yet

Fees

2026/27 schedule, GST included. Corridor access request: minor work $207, standard $460, major $713, project $1,725 (standard, major and project add the actual cost of additional work), global request for minor work at multiple sites $1,035. TMP application, which includes road closure for work on the road, $250 (complex plans at actual cost). Extension for TMP and/or CAR $150. Event road closure administration $690 per event and group of roads up to 10 km. Extra fee $324 for unauthorised or un-notified activity in the road reserve; non-compliance inspection $165 per hour.

Sources (2)
Processing time

No general lead time is published. Project works need a preliminary notification (no charge), and a project submitted without one may pay an extra processing fee if approval is needed in under 28 days. Minor and standard work is priced on a duration of under 14 days from start to final reinstatement and works completion notice, major work under 28 days.

Sources (1)

Closures and road space

Road closure application

For road works, the TMP application fee includes road closure for work on the road. For events, an administration fee applies per event and group of roads up to 10 km, and advertising and traffic management are the organiser's cost. No separate closure form or lead time was found on the pages checked.

Sources (1)
Extra forms with a CAR

Forms the council publishes beside the CAR.

  • Corridor Access Request Form (2020)

    Covers The CAR for work in the public road area

    Applies when Utility operators and others working in the road corridor

    Open the form

  • Traffic Management Plan: Full Form

    Covers A TMP for work with several phases or delays, such as resealing, shoulder widening or road reconstruction

    Applies when Complex work; a shortened form is available for simpler work

    Open the form

  • Enclose Portion of Road Application Form

    Covers Fencing part of the road reserve

    Applies when Someone wants to fence the road reserve

Sources (1)
Road space booking

Not found yet

Temporary speed limits

Not found yet

Events

Not found yet

People to notify

Public transport

Not found yet

Other notifications

Not found yet

Contacts and restrictions

Corridor access team

Roading team: [email protected], +64 3 689 0000.

Sources (1)
Working hours and restrictions

Not found yet