Selwyn District Council
What Selwyn District Council asks for when you lodge a Corridor Access Request, with the page each answer came from.
This is our summary of what the authority publishes. Check the authority's own page before you lodge.
Lodging soon? Check your TMP with the Xuro Review Engine before it goes in. See the Review Engine
Submitting
- Where to submit a CAR
myWorksites (online).
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- When a CAR is needed
A CAR is required for any activity in the road corridor. Works that do not involve ground disturbance count as non-excavation activities. Works over 10 working days, and all subdivision-related activities, fall in the project category. Emergency works by contracted maintenance and utility providers are an exception.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- TMP submission
The council asks for a TMP that suits the site and activity and is aligned with the NZGTTM. All documents must be portrait PDFs, each no larger than 15 MB. TMP approval is required before any TTM is placed in the road corridor.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- Standard accepted
NZGTTM. The council says temporary traffic management must be planned, implemented and managed in accordance with the NZGTTM. No CoPTTM position was found.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- Local conditions
Evidence of meaningful engagement with affected residents and other impacted stakeholders must be provided. A contractor may be removed from the road corridor in the situations the council lists. A Works Completion Notice is submitted when the works are finished (a template is on the council's page).
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- Fees
Fees apply from 1 July 2026. Non-excavation CAR and TMP $106, small excavation CAR and TMP $428, large excavation CAR and TMP $857. A road closure application is $2,010 in addition to the CAR and TMP fee. Road space bookings relating to a global CAR $59. Non-conforming or dangerous audit inspection and review $1,073.
Sources (1)
- Selwyn District Council - Fees and Charges checked 30 October 2026
- Processing time
Minimum processing times: project CAR/TMP 10 working days, road closure 10 working days, event road closure TMP 10 working days, road space booking (under a global CAR only) 5 working days. The council says the time to process an application depends on the request.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
Closures and road space
- Road closure application
This applies to any works requiring full closure of the road corridor to the public. The council's minimum processing time for a road closure is 10 working days, and a road closure application fee is charged in addition to the CAR and TMP fee. Public notification by the council is in addition to any agreed communication measures such as letter drops and on-site signage, which remain the contractor's responsibility. No separate road closure form was found.
Sources (2)
- Selwyn District Council - Working on the road checked 30 October 2026
- Selwyn District Council - Fees and Charges checked 30 October 2026
- Extra forms with a CAR
Forms the council publishes for corridor work.
Road Space Booking (RSB) form
Covers Booking road space under a global CAR
Applies when Working under a global CAR; road space bookings must be used before any works start
TMP Extension form
Covers Extending an existing TMP
Applies when An existing TMP needs an extension
Works Completion Notice
Covers Telling the council the works are finished
Applies when On completion of the works
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- Road space booking
Road space booking is carried out under a global CAR only, and bookings must be used before any works start. The fee is $59 per booking and the minimum processing time is 5 working days.
Sources (2)
- Selwyn District Council - Working on the road checked 30 October 2026
- Selwyn District Council - Fees and Charges checked 30 October 2026
- Temporary speed limits
Not found yet
- Events
Event road closure TMPs have a 10 working day minimum processing time. Community and sporting events that meet the council's definition are not charged for the CAR and TMP.
Sources (2)
- Selwyn District Council - Working on the road checked 30 October 2026
- Selwyn District Council - Fees and Charges checked 30 October 2026
People to notify
- Public transport
Not found yet
- Other notifications
Stakeholders to be consulted include affected residents, businesses, property owners, public transport operators, emergency services, schools, utility operators and, where applicable, the Road Controlling Authority. Contractors must obtain relevant service plans and arrange for the location of underground services.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
Contacts and restrictions
- Corridor access team
Corridor manager team: [email protected].
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026
- Working hours and restrictions
Road works are not permitted on specified roads during peak traffic periods, Monday to Friday, except by prior written approval from the Road Network Coordinator. The morning peak is 7:00 to 9:00 am. All works must cease at least 45 minutes before and after school drop-off and pick-up times, and footpaths must remain open within 100 metres of any school, high school or preschool. Which roads count as specified was not found.
Sources (1)
- Selwyn District Council - Working on the road checked 30 October 2026