Kāpiti Coast District Council
What Kāpiti Coast District Council asks for when you lodge a Corridor Access Request, with the page each answer came from.
This is our summary of what the authority publishes. Check the authority's own page before you lodge.
Lodging soon? Check your TMP with the Xuro Review Engine before it goes in. See the Review Engine
Submitting
- Where to submit a CAR
The council's CAR page tells applicants to submit through the Before U Dig website (which also checks for underground services) and says that service is the mechanism for making a CAR and giving the council a TMP. The same page also has a Submitica section and says users must set up a Submitica account to submit CARs, so confirm with the council which route applies. Before U Dig has no information on council water, wastewater or stormwater pipes, which are on the council's own mapping.
Sources (1)
- Corridor access requests - Kāpiti Coast District Council checked 30 October 2026
- When a CAR is needed
A CAR and a Works Access Permit are needed before working in the legal road. Examples listed: trenching, footpaths and entrances, work in the berm or shoulder, tree work, scaffolding and crane work. Other events or activities in the road (non-excavation) do not need a CAR and WAP but still need a TMP.
Sources (1)
- Corridor access requests - Kāpiti Coast District Council checked 30 October 2026
- TMP submission
The council's TMP page offers its own short form and long (full) form TMP downloads (Word), each with guidelines, and an on-site record form. The short form is only for simple activities where work is not in a live traffic lane (vehicle crossing or footpath construction, shoulder or grass verge work, inspections); the full form is for all other work and for generic plans.
Sources (1)
- Traffic management plans (TMPs) - Kāpiti Coast District Council checked 30 October 2026
- Standard accepted
NZGTTM. The council's TMP page (updated 2 September 2026) says TMPs must be in accordance with NZGTTM and completed by an STMS with a current NZTA qualification.
Sources (1)
- Traffic management plans (TMPs) - Kāpiti Coast District Council checked 30 October 2026
- Local conditions
Not found yet
- Fees
2026/27 schedule: CAR project works $1,330 (7 hours), major works $570 (3 hours), minor works $190 (1 hour), inspection $190 per hour. The page does not say whether GST is included.
Sources (1)
- Access and transport charges - Kāpiti Coast District Council checked 30 October 2026
- Processing time
TMP submission lead times: a TMP for a road closure at least 60 working days before the event or activity; at least 5 working days before short-term or mobile works with no closure; at least 10 working days before long-term works with no closure.
Sources (1)
- Traffic management plans (TMPs) - Kāpiti Coast District Council checked 30 October 2026
Closures and road space
- Road closure application
For a full or partial closure submit a TMP 60 days before the event (the timeframes list says 60 working days, so allow the longer). The council must advertise all road closures by law and the applicant or organiser pays. The CAR page, in its Submitica section, says to ask the road owner's permission before closing a road, restricting access or digging under a road. The pages checked name no separate closure form.
Sources (2)
- Traffic management plans (TMPs) - Kāpiti Coast District Council checked 30 October 2026
- Corridor access requests - Kāpiti Coast District Council checked 30 October 2026
- Extra forms with a CAR
Not found yet
- Road space booking
Not found yet
- Temporary speed limits
Not found yet
- Events
Street parades, cycle races, and running or walking events do not need a CAR and WAP but still need a TMP. If the event closes a road, the TMP and closure timing above apply.
Sources (1)
- Traffic management plans (TMPs) - Kāpiti Coast District Council checked 30 October 2026
People to notify
- Public transport
Not found yet
- Other notifications
Not found yet
Contacts and restrictions
- Corridor access team
Council: [email protected], 04 296 4700 (toll free 0800 486 486). For Submitica help the council points to RAMM Support.
Sources (1)
- Corridor access requests - Kāpiti Coast District Council checked 30 October 2026
- Working hours and restrictions
Not found yet