Horowhenua District Council
What Horowhenua District Council asks for when you lodge a Corridor Access Request, with the page each answer came from.
This is our summary of what the authority publishes. Check the authority's own page before you lodge.
Lodging soon? Check your TMP with the Xuro Review Engine before it goes in. See the Review Engine
Submitting
- Where to submit a CAR
Excavation CARs go through beforeUdig, which generates the CAR for the council. Non-excavation CARs go through the CorridorAccess website. The non-excavation page also says to email the TMP to the CAR requests inbox, while the traffic management page says TMPs must be lodged through the electronic CAR system and not emailed to the council, so check with the Roading Team which applies.
Sources (3)
- Applying for a Corridor Access Request - Excavation - Horowhenua District Council checked 30 October 2026
- Applying for a Corridor Access Request (CAR) - No Excavation - Horowhenua District Council checked 30 October 2026
- Traffic Management & Road Closures - Horowhenua District Council checked 30 October 2026
- When a CAR is needed
A CAR is needed for any work in the Transport Corridor, including trenching, footpaths and entranceways, work in the berm or shoulder, street parades, tree work, scaffolding and crane work. The fee schedule notes say a CAR and TMP are required for all activities that need an excavation in the berm, footpath or carriageway, and for all activities that affect normal operating conditions of the road or footpath. A CAR is not required for non-excavation work on existing utility infrastructure that does not affect the normal use of the carriageway or footpath. If the work adjoins a state highway, NZTA also requires a CAR.
Sources (2)
- Working on the Road - Horowhenua District Council checked 30 October 2026
- Roading - Fees & Charges - Horowhenua District Council checked 30 October 2026
- TMP submission
A TMP must be submitted when you apply for the CAR. It must be drawn up by a qualified STMS (the CAR pages say a person holding the STMS Level 1 qualification). The traffic management page says TMPs must be lodged electronically through the Electronic Corridor Access Request System and not emailed or posted to the council, but the non-excavation CAR page says to email the TMP to the CAR requests inbox after logging the job, so check with the Roading Team. No file format is published.
Sources (3)
- Applying for a Corridor Access Request - Excavation - Horowhenua District Council checked 30 October 2026
- Traffic Management & Road Closures - Horowhenua District Council checked 30 October 2026
- Applying for a Corridor Access Request - Excavation - Horowhenua District Council checked 30 October 2026
- Standard accepted
Not found yet
- Local conditions
The council issues its local conditions with each Works Access Permit. It also publishes Engineering Appendix Four, Working in Roads and Trench Construction (version dated 12 November 2012), as guidance on common practice for working in roads and trench construction in relation to development and subdivision. No separate current local conditions document was found, so check with the Roading Team.
Sources (3)
- Applying for a Corridor Access Request - Excavation - Horowhenua District Council checked 30 October 2026
- Working on the Road - Horowhenua District Council checked 30 October 2026
- Applying for a Corridor Access Request - Excavation - Horowhenua District Council checked 30 October 2026
- Fees
2026/27 schedule (from 1 July 2026 to 30 June 2027), GST inclusive: events $212.50 (no fee for non-profit organisations), minor works $117, major works $265.50, minor projects $313.50, major projects by negotiation, generic TMP $478, blanket CAR by negotiation. Charges also apply for works without a WAP or TMP ($1,500), stop work orders ($185) and temporary road closure public notification ($233.50). The council says it may review fees at any time.
Sources (1)
- Roading - Fees & Charges - Horowhenua District Council checked 30 October 2026
- Processing time
No current processing time is published on the CAR pages. The council's Engineering Appendix Four (version 12 November 2012), written for utility operators and contractors, says the CAR must be submitted at least five working days before minor works and 15 working days before major works and project works in roads, unless otherwise agreed, and that work must not start until a WAP has been issued or 15 working days after the CAR is lodged, whichever comes first.
Sources (1)
- engineering-appendix-four-working-in-roads-and-trench-construction-version-12-november-2012.pdf checked 30 October 2026
Closures and road space
- Road closure application
A TMP is required for an event or work that may need a road or footpath closed, and it is lodged in the CAR system. The council must advertise all road closures by law and the applicant pays the advertising cost, charged at cost. A temporary road closure public notification fee is also listed in the fee schedule. No separate road closure form or lead time is published on the pages checked.
Sources (2)
- Traffic Management & Road Closures - Horowhenua District Council checked 30 October 2026
- Traffic Management & Road Closures - Horowhenua District Council checked 30 October 2026
- Extra forms with a CAR
Not found yet
- Road space booking
Not found yet
- Temporary speed limits
Not found yet
- Events
Events that may affect vehicle or pedestrian traffic, increase traffic to an area, need a road or footpath closed, or need road signs require a TMP submitted to the council, lodged through the CAR system. The fee notes say a CAR and TMP are required for all events that affect the normal operating conditions of the road, on or off the road reserve. Sporting and non-commercial groups can ask the Manawatu Events Equipment Trust about hiring traffic management equipment.
Sources (2)
- Traffic Management & Road Closures - Horowhenua District Council checked 30 October 2026
- Roading - Fees & Charges - Horowhenua District Council checked 30 October 2026
People to notify
- Public transport
Not found yet
- Other notifications
If the work adjoins a state highway, NZTA also requires a CAR and its own approval. The council's Engineering Appendix Four (2012) says the WAP may specify communications such as a leaflet to the public at least one month before work starts, or newspaper notice or a leaflet drop at least two working days before work starts.
Sources (2)
- Working on the Road - Horowhenua District Council checked 30 October 2026
- engineering-appendix-four-working-in-roads-and-trench-construction-version-12-november-2012.pdf checked 30 October 2026
Contacts and restrictions
- Corridor access team
Roading Team: [email protected], (06) 366 0999.
Sources (1)
- Applying for a Corridor Access Request (CAR) - No Excavation - Horowhenua District Council checked 30 October 2026
- Working hours and restrictions
Council's Engineering Appendix Four (version dated 12 November 2012): construction work only 7am to 7pm Monday to Friday and 8am to 4pm Saturday, with no work on Sundays or public holidays and none outside those hours without written approval. Work is to be outside peak traffic flows (emergency works excepted) unless agreed. The appendix is a 2012 version, so confirm the hours with the Roading Team.
Sources (1)