Grey District Council

What Grey District Council asks for when you lodge a Corridor Access Request, with the page each answer came from.

Region
West Coast
Type
District council
Authority website
www.greydc.govt.nz

This is our summary of what the authority publishes. Check the authority's own page before you lodge.

Lodging soon? Check your TMP with the Xuro Review Engine before it goes in. See the Review Engine

Submitting

Where to submit a CAR

By email to the council's assets CAR inbox, [email protected]. No online portal is named on the page.

Sources (1)
When a CAR is needed

Currently a CAR is only needed in the Grey District where the activity breaks ground in the road corridor or risks damaging it. The National Code of Practice for Utility Operators' Access to the Transport Corridors is the standard for working in the road and for the CAR process.

Sources (1)
TMP submission

Email TMPs to the council's assets TMP inbox, [email protected]. A TMP is required for all activities that vary the normal operating conditions of a road (carriageway, footpath or shoulder), and may be needed for activities outside the road reserve that affect it. The designer must be suitably qualified. No file format is published.

Sources (1)
Standard accepted

CoPTTM. The council's page says TMPs must meet the minimum standards in the Code of Practice for Temporary Traffic Management. No NZGTTM position or switch date was found.

Sources (1)
Local conditions

Not found yet

Fees

2026/27 schedule, GST included. Road Works Consent / Corridor Access Request (CAR) $207. Additional inspection fee at staff hourly charge-out rates. A roadworks consent on a state highway is $880 (includes a $500 NZTA fee). Temporary use of a legal road is charged per square metre (contact the council). No TMP or road closure fee was found in the schedule.

Sources (1)
Processing time

Minimum timeframes: TMP 5 working days, CAR 10 working days, non-event road closure TMP 10 working days, event road closure TMP 42 days.

Sources (1)

Closures and road space

Road closure application

A road closure goes through the TMP and a temporary road closure application form, reviewed by the council's Traffic Management Coordinator. If the application succeeds, you get the closure form, the TMP and any conditions. The closure must then be advertised: for road works, notifications may need 5 days before with pre-warning signage and a letter drop; for events, an advertisement in the daily newspaper 42 days before. The council arranges the paper advertising and charges the contractor. You may only close the roads, dates and times stated in the accepted form and TMP.

Sources (1)
Extra forms with a CAR

Not found yet

Road space booking

Not found yet

Temporary speed limits

Not found yet

Events

An event road closure TMP has a 42 day minimum timeframe and the closure is advertised in the daily newspaper 42 days before the event.

Sources (1)

People to notify

Public transport

Not found yet

Other notifications

For road works closures, notifications may need 5 days notice, with pre-warning signage and a letter drop before works start. The contractor delivers the notification letter to affected properties and installs the on-site pre-closure signage set out in the TMP.

Sources (1)

Contacts and restrictions

Corridor access team

CAR inbox: [email protected]. TMP inbox: [email protected].

Sources (1)
Working hours and restrictions

Not found yet